Time & Work — Advanced Exam Problems

Time & Work के advanced सवाल

title

Time & Work — Advanced Exam Problems

  • Time & Work
  • Time & Work — Advanced Exam Problems
नमस्ते दोस्तों, कैसे हैं आप सब? चलिए आज की class शुरू करते हैं। आज हम सीखेंगे — Time & Work के advanced सवाल। घबराइए मत, हम एकदम basic से शुरू करेंगे। Ready? चलिए!
Scene 1/14
Learning Objective

Master phase-wise counting — workers leaving mid-way, alternate-day duty and mixed men-women teams.

🎯 Learning Objective

Master phase-wise counting — workers leaving mid-way, alternate-day duty and mixed men-women teams.

💡 Concept

  • Phase problems: someone joins or leaves mid-way — break the timeline into phases and count units in each
  • Alternate-day work: A and B form a two-day cycle; finish full cycles, then the leftover goes to whoever's turn it is
  • 'Worked x days then left' → the remaining fraction and remaining days fix the finisher's rate
  • Mixed workforce (men + women): equate the total work of two teams to link the two unit rates
  • RRB twist: the LAST unit is done at ONE person's rate — fraction-of-a-day answers are normal

🧮 Key Formulas

Alternate days: cycle work = (a + b) units per 2 days

>

Phase method: work done = rate × days, phase by phase

>

Team equality: D₁ × (team₁ rate) = D₂ × (team₂ rate) = total work

✏️ Easy Example

Q. A can do a work in 12 days and B in 18 days. They start together but A leaves after 4 days. In how many more days will B finish the remaining work?

  1. Total work = LCM(12, 18) = 36 units — LCM keeps every rate a whole number
  2. A = 3 units/day, B = 2 units/day; together 5 units/day
  3. In 4 days together they finish 5 × 4 = 20 units, leaving 36 − 20 = 16
  4. B alone at 2 units/day needs 16/2 = 8 days

Answer: 8 days

🇮🇳 Real-Life Example

On construction sites labour changes daily — contractors mentally re-run this phase maths every time a mason leaves early.

📝 Exam-Level Example

Q. A can do a piece of work in 9 days and B in 12 days. They work on alternate days with A starting. In how many days will the work be completed?

  1. Work = LCM(9, 12) = 36 units; rates A = 4, B = 3 — alternate-day questions demand unit rates
  2. One full A+B cycle (2 days) = 4 + 3 = 7 units; never average alternate work, count in cycles
  3. 5 cycles = 10 days = 35 units — stop at the largest total BELOW 36, never overshoot
  4. 1 unit is left; day 11 belongs to A (he started, so odd days are his), and A does 4 units in a full day
  5. A needs 1/4 of a day for 1 unit → total time = 10 + 1/4 = 10¼ days

Answer: 10¼ days (10.25 days)

📝 Exam-Level Example

Q. A and B together can finish a work in 30 days. They worked together for 20 days, then B left. A finished the remaining work in 20 more days. In how many days can A alone do the whole work?

  1. Together they do 1/30 of the work per day, so in 20 days they finish 20/30 = 2/3 — track the finished fraction first
  2. Remaining work = 1 − 2/3 = 1/3
  3. A alone did this 1/3 in 20 days — that single fact fixes A's rate
  4. A's rate = (1/3) ÷ 20 = 1/60 of the work per day
  5. So A alone needs 60 days for the full job

Answer: 60 days

📝 Exam-Level Example

Q. 2 men and 3 women can do a work in 10 days, while 3 men and 2 women can do the same work in 8 days. In how many days will 2 women alone do it?

  1. Let 1 man do m units/day and 1 woman w units/day — the same job gives one equation from each team
  2. Equal work: 10(2m + 3w) = 8(3m + 2w) → 20m + 30w = 24m + 16w
  3. 14w = 4m → m = 3.5w — one man produces as much as 3.5 women here
  4. Total work = 10(2m + 3w) = 10(7w + 3w) = 100w units, substituting m = 3.5w
  5. 2 women work at 2w per day → 100w ÷ 2w = 50 days

Answer: 50 days

🪄 Memory Trick

In alternate-day problems, clear the largest full-cycle total below the work, then hand the leftover to whoever's turn it is — most wrong answers come from blindly finishing the cycle.

⚠️ Common Mistakes

  • ❌ Completing the last cycle fully when the work ends mid-day (counting 42 units when only 36 exist)
  • ❌ Using the combined rate for the phase AFTER a worker has left
  • ❌ Treating men and women as the same unit before the equation links m and w

🏆 Exam Tips

  • ✅ LCM units first, always — every advanced pattern reduces to unit counting
  • ✅ Fraction tracking (2/3 done, 1/3 left) works even when individual rates are unknown
  • ✅ Write each phase on its own line: who worked, at what rate, for how long

📌 Summary

  • Advanced = phases; solve each phase with unit rates
  • Alternate days → full cycles first, then the leftover turn
  • Someone leaves → split the timeline at that moment
  • Two team equations → link m and w, then count units